Riverside Warehouse Slab

Industrial, completed 2024

Replacing the floor slab of a working distribution warehouse without closing it.

The building had to keep receiving and dispatching throughout, so we split the floor into three bays and worked one at a time, each with its own temporary racking relocation and a dust-sealed hoarding line.

Each bay was broken out, the sub-base regraded and compacted, and a 200mm reinforced slab poured with a laser screed. Joints were saw-cut within eight hours and later filled with semi-rigid epoxy so forklift wheels cross them without chipping.

Final floor flatness was measured at FF 42 against a specified FF 35. The client did not miss a single delivery in four months.

Enquire about this project

Want something like this built?

Tell us what you have in mind and an estimator will call you within one working day.

    Ready to start?

    Book a free site visit this week

    Free estimate

    Where should we send your quote?

    An estimator will call you within one working day to book a free site visit.